top of page
AlexanBothellApartments.jpeg
UPCOMING CONSTRUCTION
Start Date
Task
Duration
Neighborhood Impacts
Ongoing
Demo existing sidewalks, pour new sidewalks, landscaping, light poles around Alexan Main St
Expected Completion Sep 2024
Heavy equipment moving around site, temp sidewalk closures around Alexan Main St, possible temporary lane closures
Sep 5
Paving Main Street
2 days
Road closures during paving operations. Traffic lane changes after paving is complete
Ongoing
Completing interior finishes in Alexan Bothell
September 2024
Alexan Bothell project expected completion is September 2024 at which point units will be available for viewing
Sep 13
Paving 98th, parts of 522
1 week
Road closure during paving operations. Traffic lane changes after paving is complete
bottom of page